Concrete Street and Sidewalk Replacement Project (Various Wards)

Each year the City has an annual concrete street and sidewalk replacement project to improve many of the City’s local streets in residential subdivisions.  This project is bid during the late winter and work occurs throughout the year. (Budgeted Construction Cost = $850,000)

Asphalt Resurfacing Project (Various Wards)

Each year the City has an annual resurfacing project, which improves many of the City’s asphalt roads.  During June, the City will be resurfacing the following City Streets: 

  • Hencken Road
  • Bouquet Road
  • Bassett Road
  • Taylor Road (Route 109 to south of Sandalwood Creek Drive)
  • Ossenfort Road (Route T to Melrose)
  • Eatherton Road (Manchester Road to Cambury)

(Budgeted Construction Cost = $600,000)  

Birch Forest Drive Turn Around (Ward 5)

This project will remove the existing temporary asphalt cul-de-sac located at the end of Birch Forest Drive (West) and replace it with a permanent turnaround.  (Budgeted Construction Cost = $100,000)

Strecker Road Sidewalk Project (Ward 2 and Ward 4)

The goal of this project is to provide a continuous sidewalk along Strecker Road between Englebrook Drive to the Ellisville City Limit. The first phase of the project will construct an 850’ long segment of sidewalk from Englebrook Drive to the east. (Budgeted Construction Cost = $235,000)

Woods Road Flood Mitigation (Ward 6 and Ward 8)

This project will reduce the occurrence of flooding on Woods Avenue, between State Route 109 and Manchester Road. The project will remove and replace several existing hydraulically deficient culverts and improve the channel. (Budgeted Construction Cost = $800,000, Budgeted Final Design Cost = $85,000)

Route 109 Sidewalk Improvement Project (Ward 8) 

This project will construct a new sidewalk, with streetlights and landscaping, along the east side of Route 109, from Manchester Road to Viola Gill Lane. (Budgeted Construction Cost = $150,000)

Center Avenue Reconstruction (Ward 8)

This project will resurface and widen Center Avenue, from Manchester Road to Bordeaux Estates Ct./Falstone Mill Ct.  (Budgeted Construction Cost = $300,000)

2023 - Manchester Road and Taylor Road Resurfacing and Traffic Signal Improvement Project (Ward 7 and Ward 8)

This project will upgrade the City’s three traffic signals (Manchester Road at Pierside Lane, Manchester Road at Schnucks Wildwood Crossing, and Taylor Road at Main Street) as well as resurface Taylor Road from Manchester Road to Route 100 and resurface Manchester Road from east of Old Fairway to Route 100. Design of this project is underway.  The city is expecting to receive federal funds to construct the project. 

  • Budgeted Construction Cost = $1,800,000 ($360,000 City + $1,440,000 Federal) (2023)
  • Budgeted Design Cost = $50,000 (2021) 

2023 - Route 109 and BA South Roundabout (Ward 1 and Ward 3)

This project will construct a new roundabout at the intersection of Hwy 109 and Route BA South (Babler Park Dr). This project will reduce traffic congestion and safety at the intersection.

  • Budgeted Construction Cost = $1,465,000 = $293,000 City + $1,172,000 Federal (2023)
  • Budgeted Design Cost = $185,000 (2021)
  • Budgeted Right of Way Cost = $50,000 (2022)
  • Planned Construction Year - 2023

2023 - Bridge 386 & Bridge 387 over Wild Horse Creek - Replacement (Ward 1)

This project will prepare remove and replace Bridge #386 and Bridge #387 over Wildhorse Creek on Wild Horse Creek Road.   The city received federal funding for this project.

  • Budgeted Construction Cost = $1,700,000 ($340,000 City + $1,360,000 Federal) 2023
  • Budgeted Right of Way Cost = $30,000 (2022)
  • Budgeted Final Design Cost = $150,000 (2020)
  • Planned Construction Year = 2023

2024 - Strecker Road Sidewalks – Segment E/F

This project will complete sidewalks on the south side of Strecker Rd from Timber Ridge Estates Dr southeast to Strecker Pines Ct.

  • Budgeted Construction Cost = $200,000 (Construct in 2024)
  • Budgeted Right of Way Cost = $50,000 (2023)
  • Budgeted Design Cost = $25,000 (2022)

 2024 - Eatherton Road Improvement Project (Ward 8)

The City is designing improvements to Eatherton Road from Manchester Road north to Cambury Lane. The improved road is proposed to include a sidewalk (along the west side), 10’ trail (along the east side), storm sewers, and lighting.  

  • Budgeted Construction Cost = $2,650,000 (Construct in 2024)
  • Budgeted Right of Way Cost = $250,000 (2023)
  • Budgeted Final Design Cost = $95,000 (2022)

 2024 - Alt Road Flood Mitigation Project (Ward 6)

This project will re-build and raise a section of Alt Road at State Route 109 to provide flood free access. 

  • Budgeted Construction Cost = $750,000 (Construct in 2024)
  • Budgeted Right of Way Cost = $15,000 (2023)
  • Budgeted Final Design Cost = $30,000 (2023)

 2024 - Fullerton Meadows Median Islands (Ward 5)

This project consists of installing median islands in the widest portion of Fullerton Meadows Drive from approximately Balaji Court west to just west of Shiva Ct. The median islands will provide traffic calming and improve aesthetics.

  • Budgeted Construction Cost = $125,000 (Construct in 2024)

 2024 - Bouquet Road Culverts #340 and #352 Replacement (Ward 6)

This project will remove and replace two existing structurally deficient concrete box culverts under Bouquet Road. 

  • Budgeted Construction Cost = $800,000 (Construct in 2024)
  • Budgeted Right of Way Cost = $25,000 (2023)
  • Budgeted Final Design = $50,000 (2022) 

2025 - Old State Road Shared Use Path (Ward 7 and Ward 8)

This project will construct a new shared use path, on the north side of Old State Rd, from Nantucket Meadows Dr east to Old State Pl Dr.

  • Budgeted Construction Cost = $1,140,000 (Construct in 2025)
  • Budgeted Right of Way Cost = $100,000 (2025)
  • Budgeted Final Design Cost = $160,000 (2024)

 2025 - Pond Grover Loop Median Islands (Ward 5)

This project consists of installing median islands in the widest portion of Pond Grover Loop Dr.   from approximately Hwy 109 east to the new Pond Grover Park. The median islands will provide traffic calming and improve aesthetics.

  • Budgeted Construction Cost = $175,000 (Construct in 2025)

 2025 - Bridge 385 and Replacements (Ward 1)

This project will replace Bridges #385 over a tributary of Wildhorse Creek on Ossenfort Road.

  • Budgeted Construction Cost = $850,000 (Construct in 2025)
  • Budgeted Right of Way Cost = $30,000 (2024)
  • Budgeted Final Design Cost = $S85,000 (2022)