September 26, 2018
The contractor has completed the project and Wild Horse Creek Road is now OPEN! Gershenson Construction completed the project over one month ahead of the initial schedule. There may still be some miscellaneous clean up work in the area and they will paint the barrier walls to replicate the look of natural stone over the next few weeks as weather allows. Thank you for your patience during this improvement project.
August 22, 2018
The contractor has completed the bridge substructure and placed the steel beams. They will continue forming the deck over the next few weeks as weather allows. The project is still on schedule for completion in late October.
August 1, 2018
The contractor closed Wild Horse Creek Road and began work on the project today. The signed detour route is along Route 109 and Route 100 and will be in place for the duration of construction.
Project Overview
The contractor is scheduled to begin this bridge replacement project to replace the bridge on Wild Horse Creek Road over a tributary to Wild Horse Creek located just north of Babler Forest Road on August 1. Wild Horse Creek Road will be closed at the bridge location from August 1 through October 29 while the new bridge is constructed. The signed detour route will be along Route 109 and Route 100.