Pedestrian Bridge over Route 100

Pedestrian Bridge Updates:

May 1, 2017:

The contractor has completed the retaining walls on the north and south bridge approach areas will complete some of the approach trail work in May as the bridge structure is being fabricated. The bridge structure is expected to be delivered and installed in June. Please use caution when traveling through the work areas. A pedestrian bypass has been installed on the north bridge approach to provide for continued pedestrian access during the project.

February 24, 2017:


The contractor has completed the foundations for the new bridge and will continue constructing the retaining walls on the north and south bridge approach areas over the next few weeks as weather allows.  The contractor will complete some of the approach trail work in March and April as the bridge structure is being fabricated.  The bridge structure is expected to be delivered and installed in May.  Please use caution when traveling through the work areas.  A pedestrian bypass has been installed on the north bridge approach to provide for continued pedestrian access during the project.

January 10, 2017:

The contractor has been constructing the retaining wall on the north bridge approach area has also began on the center bridge pier in the median of Route 100.  Work will continue over the next few months as weather allows.  Please use caution when traveling through the work areas.  A pedestrian bypass has been installed on the north bridge approach to provide for continued pedestrian access during the project.

December 14, 2016:

The contractor has began excavation work for the retaining wall on the north bridge approach area.  They will begin installing the retaining wall over the next few weeks.  Work has also began on the center bridge pier in the median of Route 100, and will continue over the next few months as weather allows.  Please use caution when traveling through the work areas.  A pedestrian bypass has been installed on the north bridge approach to provide for continued pedestrian access during the project.

December 2, 2016:

The contractor has began work on this project with clearing of the north and south bridge approach areas.  They will begin working on the center bridge pier in the median of Route 100 in the next few weeks.  Work will also begin on the retaining walls along the north and south bridge approach areas over the next month as weather allows.  Please use caution when traveling through the work areas.  A pedestrian bypass will be installed on the north bridge approach area as necessary to provide for continued pedestrian access during the project.  A pedestrian bypass will not be necessary on the south side trail as the existing trail will remain in place for the duration of the project.

PROJECT OVERVIEW:

This project will construct a new Pedestrian Bridge over Route 100, from the existing trail near the end of Kilare Lane on the south side of Route 100 to the existing trail near the end of Eatherton Road on the north side of Route 100.  This project will begin in late 2016 and is scheduled to be completed by the end of the summer of 2017.